1) Preparation
Plan how the rainwater will drain away, e.g. via an existing underground pipe or a nearby trench. Recommended tools for installation: rubber mallet, spirit level and string with holding rods.
Plan how the rainwater will drain away, e.g. via an existing underground pipe or a nearby trench. Recommended tools for installation: rubber mallet, spirit level and string with holding rods.
Remove the paving stones and dig a trench.
y = 20 cm + HYDROblock height (up to D 400) or y = 25 cm + HYDROblock height (up to F 900)
x = 30 cm + HYDROblock width (up to D 400) or x = 40 cm + HYDROblock width (up to F 900)
Determine the course of the drainage channel with a string. The string is also used later for levelling the channel elements. The height of the string should be 3 mm below the top edge of the paving.
The drainage channel installation begins with the outlet element. Both drain elements with vertical outlet and feed boxes can be used for this purpose. Alternatively, the spigot end of the HYDROblock can be used to connect a pipe. When using a feed box, the trench must be excavated deeper.
Extend the underground pipe with a pipe joint. Place a concrete foundation with a grade of C25/30 in the trench.
z = 20 cm (up to D 400) or z = 25 cm (up to F 900).
The channel elements are set when the concrete is earth-moist.
Place the outlet element on the underground pipe. The pipe opening is closed until installation is complete so that no dirt can get into the pipe.
Apply lubricant to the spigot end before the drainage channel elements can be joined together.
First connect the channel elements loosely by spigot and socket end.
Then pull the channel elements together with the HYDROblock installation aid. For the installation of the nominal width 300, 2 installation aids are required and placed in the outer openings of the grating. For laying the channel in pedestrian design, please use our special FG laying aid. Please note that a small gap may occur when the elements are pulled together and can be closed with sealing tape.
In order to avoid movement of the drainage channel when paving, it is recommended to bolt them into the foundation with concrete screw anchors or to secure them with a concrete mounting support on the sides.
Apply a sealing tape according to ZTV Fug - Stb 15 to the long sides of the HYDROblock elements. It compensates transverse expansion.
Place the matching end pieces at the ends of the drainage channel line.
Lay the load bearing substructure and the binder course around the drainage channel.
Place the paving stones next the drainage channel. Sweep the existing sand into the joints of the paving stones. The drainage channel is then ready for use.
HYDROTEC accepts no liability for incorrect installation of the drainage channel.